Completed Projects (Infra, Building and Other Temporary Works)

NoProject / Client / ConsultantsScope of WorksContract Value (RM)Period
1Bridge over Sg. Aur  at Kelang. Asah S.B. / Lankhorst Pancabumi2 nos. Temporary steel staging working platforms in the river for the 100 ton piling rig.0.4 MillionApr 97 to  Jun 98
2Perak Hanjoong Simen (PHS) Expansion Project, PL-2 Civil and Building works. Sato Kogyo Co. Ltd / Perak HanjoongCement plant expansion works –Line 226.0 MillionJun 97 to May 00
3 Putrajaya – Prime Minister Office Masonry Works. Setia Putrajaya S.B.Bricklaying and plastering works at Main Block, West Wing.3.7 MillionFeb 98 to Nov 00
4Sekolah Kebangsaan DWI Tasik Hajadi S.B. / Kementerian Pendidikan Akitek Laras3 blocks of 4 storey school building. Works include; sludge removal & piling works,  canteen, sub-station and external infra structural works.10.8 MillionJul 01 to Jul 03
5Stormwater Management & Road Tunnel (SMART) Project Package – D5-5-4 MMCEG-Gamuda JV Sepakat Setia perunding208m long MN01/02 and MN03/04 ‘Double Box Reinforced Concrete Structure’10.6 MillionMay 04 to June 06
6Stormwater Management & Road Tunnel (SMART)  Project Package – D6-5-16 MMCEG-Gamuda JV Sepakat Setia perunding 58.2m llong MS01’ Single Box Reinforced Concrete Structure’ and 164.29m length of MS02 ‘U-Section Structure’.2.7 MillionDec 04 to July 05
7Stormwater Management & Road Tunnel (SMART)  Project Package – D5-5-19 MMCEG-Gamuda JV Sepakat Setia perunding102m long MN01/02 and 203m long MN03/04 ‘Double Box Reinforced Concrete Structure’.10.2 MillionOct 05 to May 06
8Pembinaan Jalan Pintas Rawang (Package 5A- Slope Protection and Stabilization) Panzana Enterprise S.B. Arup Perunding S.B.Slope stabilization – ‘Soil Nailing’, guniting works.2.8 MillionSep 06 to Jan 07
9Pembinaan Jalan Pintas Rawang –  (Package 6A- Arch Culvert and Drainage) Panzana Enterprise S.B. Arup Perunding S.B.300mm dia. Micro Piling Works and drainage works  for Arch Culvert2.1 MillionMar 07 to Dec 07
10Project Membina Jambatan Di Atas Sungai Pahang Di Kuala Krau, Termeloh, Franky Const. / Binaan Desjaya S.B. JKR MalaysiaConstruction Of 200m long X 6m width temporary access bridges across Sg. Pahang & Sheet pile Cofferdam to facilitate pile cap construction.34.2  MillionNov 07 to Dec 09
11Pembinaan Jalan Pintas Rawang Package 5B- Slope Protection and Stabilization Works. Panzana Enterprise S.B. Arup PerundingSlope stabilization – Soil nailing and guniting works.10.3 MillionDec 07 to Jan 12
12Pembinaan Jalan Pintas Rawang Bagi Mengatasi Kesesakan Lalulintas Di Bandar Rawang Secara ‘Design and Build’ Panzana Enterprise Sdn. Bhd. Arup PerundingPackage 12 – Reinforced Concrete Retaining Wall – Interchange South 2 LHS Construction & completion of 6m height RC retaining wall.1.24 MillionApr 11 to Feb 12
13Projek Pembinaan Pusat Latihan Gabungan Pasukan Tempur (PLGPT) Fasa IV, Kem Syed Sirajuddin, Gemas, Negeri Sembilan Darul Khusus – Panzana Enterprise Sdn. Bhd. KPS ConsultancyRiver alignment at POP_TD2.45 MillionSep 11 to  Jun 12
14Projek Pembinaan Pusat Latihan Gabungan Pasukan Tempur (PLGPT) Fasa IV, Kem Syed Sirajuddin, Gemas, Negeri Sembilan Darul Khusus – Panzana Enterprise Sdn. Bhd. KPS ConsultancyConstruction and Completion of Building Works for Garaj Jambatan12.29 MillionJun 11 to Aug 12
15Projek Construction & Completion Of RC Works Of Cooling Water Pump House & Aeration Basin For Design, Engineering, Procurement, Delivery , Construction And Commissioning Of The Manjung Coal Fired Power Plant At Manjung In Malaysia Mudajaya Corporation BerhadConstruction and Completion of RC Works of Cooling Water Pump House & Aeration Basin.27.3 MillionAug 12   to Aug 14
16Proposed Climbing Lane Between Slim River And Sungkai (Northbound) Km 371.8 To Km 387.24 PROPEL BERHADUpgrading of climbing lane for PLUS highway. Works include earthworks, drainage works, extension of culvert and etc5.5 MillionFeb 14   to Nov 14
17Duta Ulu – Kelang Expressway (DUKE) Phase 2, Section 1 – Sri Damamsara Link Pembinaan SahabatJaya Sdn. Bhd.Construction & Completion Of Hand Dug Caisson Pile Works At Mainline 1 (ML1)18.7 MillionApr 14   to May 16
18Projek Pembinaan Jalan Pintas  Rawang Bagi Mengatasi Kesesakan Lalulintas Di Bandar Rawang Secara ‘Design And Build ‘: Jajaran Alternatif  Yang Melalui Taman Warisan Negeri Selangor  (Elevated Structure) – Geotechnical Works Panzana Enterprise Sdn. Bhd.Preliminaries Works, Soil Nailing, Rock Slope  Stabilization, Reinforced Soil Wall, RC Retaining Wall, Horizontal Drain and others Associated Works.29.4 MillionJul 12   to Jun 16
19Desa Wira Jaya II, Pasir Mas, KelantanConstruction of 266 units of Single Storey Terrace House24.23 MillionJan 19 to    Dec 19
20Cadangan Pembangunaan Di Atas Tanah Kerajaan (TK) Seluas 27.12 Ekar Di Kampung Bukit Cina, Mukim Pasir Akar, Daerah Besut, Terengganu Bagi Cadangan Membina Dan Menyiapkan Pambangunan Bercampur. Wanland Metro Sdn. Bhd.Construction and completion of
a) 68 units single storey house affordable house Type A
b)280 units single storey house affordable house Type B
c) 8 unit double storey shop house.
d)Associated Infrastructure Works
44.841 MillionJul-2020 to Jul-2021 (terminated due to no payment)
21Cadangan Membina 1 Unit Rumah Banglo Kediaman 3-Tingkat Di Atas Lot 53898 (No. 43A), Jalan Bukit Segar 7, Mukim Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur Untuk Tetuan Pn. Elaine Han E Ling & Cik. Irene Han I LingSub-Contract for RE Wall Base Construction, Granular Back Filling, Slope Trimming and Drainage Works0.63 Million1 June 2021 to 30 Nov 2021

SRK DWI TASIK, Tasik Permaisuri, Cheras, KL (2003)

Completed 3 blocks of 4 storey school building and infrastructure

Storm Water Management and Road Tunnel – Jln Tun Razak. K. Lumpur WP (Year 2006)

a) 503m  MN 01/02 & MN 03/04 ‘Double RC  Structure’ – [Package D5-5-19 & D5-5-4].

b) 58.2m ‘MS 01 Single Box RC Structure’ & 164.29m MS 02 U-section structure – [Package D6-5-19]

Projek Membina Jambatan di-Atas Sg. Pahang, Kuala Krau, Temerloh (2007-2008)

Temporary steel bridge across Sg. Pahang.
Cofferdam for construction of pile cap

Rawang Bypass, Reinforced Concrete Wall & Soil Nailing Works (2011)

Completed 230m long x 6m height RC retaining wall

Gemas, Kem Syed Sirajuddin – River Alignment at POP-TD (2012)

Supply, construction and completion of river re-alignment works with Armoflex Matts 180

Gemas,  Kem Syed Sirajuddin – Garaj Jambatan (2012)

Construction and completion of Building Works
Construction and completion of Building Works

Manjung Perak, Cooling Water Pump House & Aeration Basin (2014)

Construction and completion of RC works of cooling water pump house & Aeration basin
Construction and completion of RC works of cooling water pump house & Aeration basin

DUKE, Phase II – Sri Damansara Link – Caisson Works (2015)

Construction & Completion Of Hand Dug Caisson Pile Works At Mainline 1 (ML1)

Rawang Bypass, Phase II – Geotechnical Works  (2012-2016)

RC Retaining Wall and others Associated Works.
Slope Stabilization Works

Taman Desa Wira Jaya 2A,  Pasir Mas, Kelantan (2019)

266 units Single Storey Terrace Houses

Cadangan Pembangunan Bercampur di Pasir Akar, Besut, Terengganu (2021)

Slope Construction for Cadangan Membina 1 Unit Rumah Banglo Kediaman 3-Tingkat Di Atas Lot 53898 (No. 43A), Jalan Bukit Segar 7 (2021)

RE Wall Base Construction & Granular Back Filling